PAVEMENT REHABILITATION OF HIGHWAY PR-149, JUANA DIAZ - VILLALBA

CLIENT

PR Highway Authority

San Juan PR

SCHEDULE

Started : JULY 2016

Completed : (in progress)

CONTRACT

In progress

(as subcontractor of Super Asphalt Pavement Corp)

Project Summary

This project consists of performing pavement rehabilitation at highway PR-149 from kilometer 55.80 to kilometer 73.00. It has a total length of 17.20 kilometers.


The proposed works consists, but is not limited to: cold milling of bituminous concrete pavement, full depth removal of bituminous concrete pavement, warm mix asphalt pavement Superpave SPS, pavement markings, maintenance and protection of traffic and other incidental works.


This project will be financed with combined funds from the Federal Highway Administration and the Puerto Rico Highway and Transportation Authority.

The Scope

  • 12,700 cubic meters of full depth removal of bituminous concrete pavement.
  • 1,600 cubic meters of cold-milling bituminous concrete pavement.
  • 2,250 meters for removal and replacement of corrugated steel beam guard rail.
  • 32,000 tons of hot-mix asphalt pavement.